Road Construction Updates

Updated project information will be posted as it becomes available. Please check the site regularly for the most current information.

Traffic Light Sequencing/Signalization at SR 44 and Auburn Road
We are currently working with the Ohio Department of Transportation regarding the light sequencing/signalization at SR 44 and Auburn Road. Thank you for your patience while we work to resolve the issue.

Ravenna Road Repaving Project
The Lake County Engineering Department has released an announcement that Ravenna Road is being repaved from Auburn Road to SR 608 beginning May 1, 2017. Traffic shall be maintained at all times with no road closings. Estimated completion date is July 1, 2017. ­As weather and delays may occur, please remain alert and drive safe throughout the process.

SR 608 Bridge Replacement Project
The tentative schedule for the SR 608 Bridge Replacement Project is as follows:

March 28-May 8, 2017: Phase 1 - Complete water and sewer work
April 28-August 8, 2017: Phase 2 - Construct culvert, headwalls, wingwalls, etc.
August 8-October 13, 2017: Phase 3 - Close SR 608, 45 day closure

The Greenway Pathway is closed in the area where the pathway goes under SR 608. In conjunction with the closing of the pathway, the Ravenna Road parking lot and pathway access is closed. Pathway access and parking at the Environmental Learning Center will remain available. The pathway is scheduled to reopen by late October.

­

­

­

­

­
­
­
­
­
­
­

­
­
­
­
­